Rehabilitation of Parking Area using TechCell Geocell, Lower Parel, Mumbai

Mumbai, Maharashtra, India |  Balkrishna Industries Limited, Mumbai

Overview

This case study describes the restoring of parking area by Techcell Geocell., the main application of Techcell Geocell here is to increase the level of existing parking area at the same time providing the strong base for the concrete flooring.

Challenge

The parking area of BKT Tower was very old and distress at number of places, the approach roads and other surrounding areas floor levels are comparatively higher than this parking area, so during monsoon there were lots of issue of water logging which had resulted in failure of flooring and settlement at fewer places. It is very much necessary to raise the level of existing parking and also make it durable. The site is located in the busiest area of Mumbai, i.e. in Lower Parel, the parking area and surrounded area are very much busy during weekdays, so to remove the old flooring and reconstruct the new parking area with traditional method seems to be challenging due to lack of time and space availability to store the removable materials and new materials.

Solution

Considering all the above aspects , our engineer has suggested to go for the Techcell Geocell with infill materials as grit/crushed stone above the existing parking without removing it., which will not only raise the level but also give very strong base for the concrete flooring without much hassle. The perforation of techcell Geocell also take care of the drainage function, which will not be possible in our conventional base system.

The main advantage to go for Geocell here is for the speed of construction, with the Techcell Geocell here the base prepared in only 2 days’ time without affecting the busiest parking space for vehicles and after preparing the base with techcell Geocell we can immediately use it for parking which is the need of the project.

The 3D confinement of Geocell prevents movement and shearing of soil infill under cyclic loading, while reducing aggregate attrition. The confinement system also maintains soil compaction, thereby providing long term soil reinforcement and structural strength as well as improves moduli of infill materials, while increasing the bearing capacity of the structural pavement layers of load support.

Project Outcome & Performance

Techcell’s easy, quick installs enabled the contractor to finish project work within 7days. The client was very happy with product quality as well as quality of work.

Related Sectors
Related Solutions
Related Products

Frequently Asked Questions
(FAQs)

The project aimed to restore and upgrade the parking area at BKT Tower, Lower Parel, by raising its level and providing a durable base for concrete flooring using TechCell Geocell.

  • The parking area was old and distressed at multiple locations.
  • Surrounding approach roads had higher floor levels, causing waterlogging during monsoons.
  • Flooring failures and settlement issues made the area unsafe and inconvenient.
  • Busy location in Lower Parel, Mumbai, with limited space for material storage.
  • Heavy weekday traffic made traditional reconstruction methods impractical.
  • Need for a fast, durable solution without disrupting parking operations.

TechFab India engineers recommended TechCell Geocell filled with grit/crushed stone directly above the existing parking surface.

  • This raised the level without removing old flooring.
  • Provided a strong base for concrete flooring.
  • Geocell perforations ensured drainage, solving waterlogging issues.
  • 3D confinement prevents soil movement and shearing under cyclic loading.
  • Reduces aggregate attrition and maintains compaction.
  • Improves modulus of infill materials and increases bearing capacity.
  • Provides long-term reinforcement and structural strength.
  • Speed of construction: Base prepared in only 2 days.
  • Minimal disruption to busy parking operations.
  • Immediate usability after installation.
  • Drainage function integrated into the system, unlike conventional bases.
  • Entire rehabilitation completed in 7 days.
  • Client was highly satisfied with product quality and execution.
  • Parking area raised, strengthened, and made durable against monsoon waterlogging.